NEW QUESTION # 96
Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.

  • A. Global Preferences are customized at the user level.
  • B. Global Preferences are controlled by the System Administrator
  • C. Global Preferences are controlled by Global Security Profiles.
  • D. Global Preferences are shared among all users.

Answer: A


NEW QUESTION # 97
Your customer wants to take advantage of capacity planning in portfolios. The customer would like to use generic resources, because they have greater flexibility to respond to changing costs by resource by location. In fact, they would prefer not to set up any roles at all in the database, because they perceive generic resources and roles to be duplicate effort. What would an appropriate response be to this customer?

  • A. Integrate with HR systems to obtain automated generic resource pricing updates.
  • B. User generic resources for project financials, and mirrored roles for capacity planning.
  • C. Use generic resources in Capacity Planning view, because they have greater ability to respond to changing costs.
  • D. Use roles for planning and project financials to eliminate duplicate data maintenance.

Answer: A


NEW QUESTION # 98
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?

  • A. You did not save the changes made to the activities.
  • B. You must refresh the view in the web to view the changes.
  • C. You have not completed each of the activity steps.
  • D. Your security does not allow you to update Activity Status.

Answer: B


NEW QUESTION # 99
You are a Project Manager that used Primavera P6 EPPM Web interface. You are trying to determine if some Project level User Defined Fields might be appropriate for one of your projects. You launch Primavera P6 EPPM Client to view enterprise dat a. You are unable to launch the application. What is the probable issue that must be addressed with your System Administrator?

  • A. You do not have appropriate license.
  • B. You do not have appropriate security privileges.
  • C. You are not a Responsible Manager.
  • D. You need additional memory added to your machine.

Answer: B


NEW QUESTION # 100
Identify one new feature in Release 8 related to Resource Management.

  • A. Role teams
  • B. Resource teams
  • C. Resource GANTT chart
  • D. Resource capacity versus demand

Answer: D


NEW QUESTION # 101
You are coaching a new Primavera Project Manager that is attempting to add a WBS Child element in their new project plan. The are in an Activity Table. The WBS icon is not available to this user.
What could be the problem?

  • A. They do not have security to add WBS elements
  • B. They have not selected the parent WBS element
  • C. They are not listed as the Project Manager for the project
  • D. They are not the Primary Resource for the Activity

Answer: D


NEW QUESTION # 102
You decide to add a second Detail Form to a Business Process after it has been published to production. After doing so, you must also change .

  • A. item logs
  • B. the Business Process properties
  • C. the Upper Form(s)
  • D. the workflow (s)

Answer: B


NEW QUESTION # 103
You are a Project Manager whose projects are integrated with Financial Management System (FMS). The FMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date. Updating Percent complete using the pushed Actual Dates, Actual Costs, and Actual Hours has created inaccurate pictures of the overall % complete, because there are steps within activities that clearly have not completed.Which Percent Complete Type would be the best selection for activities in this project?

  • A. Physical
  • B. Duration
  • C. Effort
  • D. Units

Answer: A


NEW QUESTION # 104
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this.

  • A. Create a Global Security Privilege for the Governance organization.
  • B. Create a custom portlet for a Governance dashboard.
  • C. Create a Global Governance Activity view.
  • D. Create a Secure Global Activity Code.
  • E. Group and sort by Governance deliverable.
  • F. Create a filter available to the Governance organization.

Answer: A,C,F


NEW QUESTION # 105
Identify two objects that cannot be changed once a Business Process has been imported into Unifier production instance.

  • A. Detail Forms
  • B. Workflows
  • C. Upper Forms
  • D. Logs
  • E. Record statuses defined as terminal

Answer: C,E


NEW QUESTION # 106
Yon are working with a customer that has had a legacy Primavera release installed and running in their environment for four years, the CIO tells you that the current EPS does not show the data the way he would like to view it, and, therefore, he would like to restructure the entire EPS. Before proceeding, what four options would you present to the CIO so that organizational Impacts are eliminated?

  • A. Identify the reporting requirements.
  • B. Modify global filters.
  • C. Restructure the OBS.
  • D. Add project codes
  • E. Modify Group and Sort.
  • F. Modify the EPS.
  • G. Create user-specific filters.

Answer: B,C,F,G


NEW QUESTION # 107
Identify the TRUE statement regarding Work Breakdown Structures (WBS).

  • A. Lowest level of WBS is Activity
  • B. The WBS is enterprise data
  • C. The EPS is top level of the WBS
  • D. WBS Root level is Project ID and Project Name

Answer: C


NEW QUESTION # 108
All commands executed by toolbar icons can be accessed from three menus. Select the three menus.

  • A. Edit
  • B. Copy
  • C. Paste
  • D. Modify
  • E. Remove
  • F. View
  • G. Action

Answer: A,D,G


NEW QUESTION # 109
Identify the true statement regarding the EPS page in P6 R8.

  • A. Any user can now copy projects on the EPS page regardless of the user,s Security profile.
  • B. You cannot copy projects on the EPS page - this must still be done in the Client.
  • C. You can copy a project on the EPS page and paste it into another EPS node.
  • D. Only application administrators have the privilege to copy/paste projects.

Answer: C


NEW QUESTION # 110
What is a resolving Condition?

  • A. a picker that auto-populates data within a workflow
  • B. a problem-solution statement within uDesigner
  • C. a solution that is created within linked fields in Forms
  • D. a path that is taken if a condition does not trigger